Substation Battery Sizing: The Complete Engineer’s Guide

Battery sizing thumbnail

Battery sizing is a critical engineering process which is used to determine the required capacity of a battery system, which has to ensure uninterrupted power supply to protection system, control system and communication equipment of the substation during normal and emergency operating conditions. The battery system must support the essential loads such as relay, circuit breaker tripping and closing, substation SCADA and emergency lighting backup for a specified duration. Proper battery sizing ensures the DC system reliability and operational safety. Accurate battery sizing prevents premature failure, voltage collapse and loss of critical functions during blackouts.

System Description and load classification

Accurate battery sizing begins with precise understanding of the DC loads to be supplied by the battery. These loads are grouped based on their behaviour during normal operation and during AC supply failure.

Continuous Load

Continuous load is that DC load which remains energized for the entire battery duty cycle (time) including normal operations and during the AC failure. It typically includes the indication lamps, trip circuit supervision relay, bay control units, communication system and other panel electronics. In IEEE battery sizing methodology, continuous load forms the base load curve and is applied for full backup duration having the highest impact on the total battery capacity.

Momentary load

Momentary load is basically the short duration, high current demand that occurs only for brief interval of time, usually during the switching or fault condition tripping. Typical example includes circuit breaker trip coils, closing coil, DC motor operated isolators. IEEE standards treat momentary loads separately from continuous loads because momentary load imposes peak current stress on the battery. These loads influences the battery’s discharge rate capability and sizing of inter cell connectors, cables.

Emergency load

This load refers to the DC loads that are energized only during abnormal or emergency conditions such as AC supply failure, system faults or protection operations. These includes emergency lighting, fire protection system. In battery sizing calculation, emergency loads are added to continuous load profile for the specified backup period to ensure that the battery can sustain critical system function until the restoration of normal AC power.

Battery Duty Cycle

The battery duty cycle represents the complete anticipated electrical loading profile that the DC battery system must support after the loss of AC power, from the instance of the AC failure till the backup period or till AC power is restored. It shows how much current the battery must deliver and at what time each load occurs and for what period are the loads connected.

The duty cycle or the load cycle of the battery combines continuous, momentary and emergency load into a single operational scenario, which reflects the worst credible operating condition of the substation.

Steps of battery sizing for 220V

Data

1. Type of battery = Valve Regulated Lead Acid type

2. Nominal Battery Voltage (NBV) = 220 V

 3. No of cells = 220/2 = 110 Nos As each VRLA cell has a voltage of 2 V (approx.)

 4. End cell voltage after discharge (for Discharge Rate of C10) = 1.8 V

 5. Load cycle considered

 a.  Continuous load (Control & Relay Panel) = 10 hours

 b.  Emergency load (Lighting) = 1 hours

 c.  Momentary load (Simultaneous Tripping) = 1 min

 6. Average electrolyte temperature = 24 Deg.C.

7. Load Determination

Panel manufacturer’ data

manufacturer's data of panel DC load for battery sizing

Continuous Load calculation

SlEquipment / PanelQuantityLoad per Unit (W)Total Load (W)
a33 kV Twin Feeder Control & Relay Panel61206 × 120 = 720
b33 kV Bus Section Control & Relay Panel161.51 × 61.5 = 61.5
c33 kV Capacitor Bank C&R Panel257.52 × 57.5 = 115
d220/33 kV Transformer LV Side C&R Panel298.52 × 98.5 = 197
e220 kV Line C&R Panel1137.51 × 137.5 = 137.5
f220/33 kV Transformer HV Side C&R Panel2168.52 × 168.5 = 337
g33 kV Bus Coupler Panel22002 × 200 = 400
h220/33 kV Transformer RTCC Panel179.51 × 79.5 = 79.5
iSwitchyard SAS Panel (RTU)1521 × 52 = 52
jSynchronizing Panel186.21 × 86.2 = 86.2
kBattery Charger22002 × 200 = 400
lFire Fighting System2152 × 15 = 30
mPLCC & FOTE22402 × 240 = 480
nMiscellaneous DC Loads0
 Total Load a+b+c+d+e+f+g+h+i+j+k+l+m+n  3095.7 W

Total continuous load current (L1)

= Total continuous load / Battery voltage = 3095.7 /220 = 14.07 A

Emergency load calculation

SlEmergency EquipmentQuantityLoad per Unit (W)Total Load (W)
aEmergency DC Lighting8 lamps100800

Total load duration selected by client as is 1 hour, as all substation breaker can be opened and control room emergency can be handled within this time period.

Emergency load current (L2) = 800/220 = 3.64 A

Momentary load calculation

Based on data from circuit breaker manufacturing sheet and panel’s manufacturer

SlEquipment / OperationBays / QtyLoad per Unit (W)Total Load (W)
a33 kV VCB – Closing Coil1 bay × 1 coil250250
b220 kV CB – Closing Coil1 bay × 1 coil330330
c33 kV VCB – Trip Coil7 bays × 1 coil2501750
d220 kV CB – Trip Coil4 bays × 1 coil3303960
e33 kV Twin Feeder C&R Panel62191314
f33 kV Bus Section C&R Panel1111111
g33 kV Capacitor Bank C&R Panel2107214
h220/33 kV Transformer LV Side C&R Panel2148296
i220 kV Line C&R Panel1196196
j220/33 kV Transformer HV Side C&R Panel2347694
k33 kV Bus Coupler Panel2300600
l220/33 kV Transformer RTCC Panel1120120
mSwitchyard SAS Panel (RTU)1103103
nSynchronizing Panel186.286.2
oBattery Charger2360720
 Total momentary load a+b+c+d+e+f+g+h+i+j+k+l+m+n+o  10744.2

Total momentary current, L3 = 10744.2/220 = 48.84 A

Load Determination

Continuous load considered for 10 hrs = 3095.7 W

Emergency load considered for 1 Hr = 800 W

Momentary load considered for 1min = 10744.2 W

Duty cycle for battery sizing

Calculation from the duty cycle

PeriodLoadsLoad Current (A)Duration (Minutes)
1L1+L2 = A117.7159
2L1 = A214.07540
3L1+L2+L3 = A366.551

The battery capacity is calculated as below

PeriodLoadChange in load (Amp)Duration of Period(minute)Time at the end of section(minute)Capacity factorRequired section size
Section-1 For first period only, If A2 is greater than A1 go to section-2
1A1A1-0 = 17.71M1 = 59T = M1 = 592.417.71 * 2.40 = 42.49
Section-1 Total42.49
Section-2 For first two periods only, If A3 is greater than A2 go to section-3
1A1A1-0 = 17.71M1 = 59T= M1 + M2 = 59910177.077
  A2-A1 = -3.64M2 = 540T = M2 = 5409.6-34.909
Section-2 Total142.168
Section-3 First 3 periods only
1A1A1-0 = 17.71M1 = 59T = M1+M2+M3 = 60010177.077
2A2A2-A1 = -3.64M2 = 540T = M2+M3 = 5419.6-34.909
3A3A3-A2 = 52.48M3 = 1T = M3 = 11.262.98
Section-3 Total205.141

The capacity factor is found out from the battery manufacturer’s discharge curve as is shown below for time at the end of section 1 that is 59 minutes.

capacity factor for Battery sizing

From the above table we find that the maximum section size is 205.141. Hence, this value is considered for further calculations.

Considering,

Design margin = 1.1                                                      As per IEEE -485

Aging factor = 1.25                                                        As per IEEE -485

Temperature correction factor = 1.01                   As per IEEE -485

Required battery capacity = 1.1 x 1.25 x 1.01 x 205.141 = 284.88 AH

Selected battery capacity = 300 AH.

Determination of battery charger capacity

Online Float charger rating

Float charger rating = 1.2 x DC average Load

Average DC load = Area of the load cycle / Time of the load cycle

= (A1 x M1 + A2 x M2 + A3 x M3) / (M1 + M2 +M3)

= (17.71 x 59 + 14.07 x 540 + 66.55 x 1) / (59 + 540 + 1)

= 8709.24 / 600 =14.51A

Therefore, float charger rating calculated = 1.2 x 14.51 = 17.41 A

Chosen float charger rating = 30 A

From the above calculation it is seen that the charger’s rating is sufficient.

Offline Boost charger rating

Boost charger rating = 10% of the AH load.

=0.10 x 300 = 30 A

Chosen boost charger rating = 45 A

From the above calculation, it is seen that the chosen boost charger capacity is sufficient since chosen rating > calculated rating.

The battery sizing calculation concludes the size of the 220 V battery bank as 300 AH and float cum boost charger rating at (30+45) = 75 A.

This article is a part of the Energy storage and reactive power compensation page, where other articles related to the topic are discussed in details.

Reference

https://standards.ieee.org/ieee/485/6726

Leave a Comment